Construction Notice for I-15 / SR 79 Temecula Parkway

Closure Notice for I-15 / SR 79 Temecula Parkway 

Roadway excavation in preparation for construction of a retaining wall and potholing in preparation for utility relocation necessitates the closure of freeway lanes and ramps in the next two weeks.

Closures Planned for July 31 – August 3, 2017

What:

  • I-15 Northbound on-ramp
  • I-15 Northbound lanes 3 and 4
  • I-15 Southbound on-ramp
  • SR-79 outer Eastbound lane from Murrieta Creek to Bedford Court.

When:

  • I-15 Northbound on-ramp will be closed July 31 – August 3, 2017 from 11 pm to 4 am
  • I-15 Northbound lanes 3 and 4 will be closed July 31 – August 3, 2017 from 11 pm to 4 am
  • I-15 Southbound on-ramp will be closed on July 31, 2017 from 9 pm to 5 am
  • SR-79 outer Eastbound lane will be closed on July 31, 2017 from 9 pm to 5 am

Closures illustrated in the diagram below. 

TemeculaClosures1579_731TemeculaClosures1579_81-3

Closures Planned for August 7 – 10, 2017

What:

  • I-15 Northbound on-ramp
  • I-15 Northbound lanes 3 and 4
  • I-15 Southbound on-ramp

When:

  • I-15 Northbound on-ramp will be closed August 7 – August 10, 2017 from 11 pm to 4 am
  • I-15 Northbound lanes 3 and 4 will be closed August 7 – August 10, 2017 from 11 pm to 4 am
  • I-15 Southbound on-ramp will be closed on August 7 – August 10, 2017 from 9 pm to 5 am

Closures illustrated in the diagram below. 

TemeculaClosures8_7-10

Please refer to detour maps # 2 and #4.

Use the following link to access detour maps on project website. https://1579south.files.wordpress.com/2017/06/detourrtemaps60717.pdf