TemeculaClosures_July10-13aTemeculaClosures_July10-13bRamp and lane closures are anticipated from Monday July 10, 2017 through Thursday July 13, 2017 to allow for the safe removal of trees, shrubs, brush and other vegetative growth along the roadside

Closures will only take place at night. Ramps and lanes will open for the morning commute and remain open through the evening commute times.

July 10, 2017 Closures Will Include:

  • North bound I15
    • Closure of lanes #3 and #4 from 11 pm to 4 am.
    • Closure of north bound on-ramp at SR 79/Temecula Parkway from 11 pm to 4 am.
    • Closure of north bound off-ramp at SR 79/Temecula Parkway from 9 pm to 5 am
  • South bound I 15
    • Closure of lanes #3 and #4 from 11 pm to 4 am.
    • Closure of southbound  off-ramp at SR 79/Temecula Parkway from 9 pm to 5 am

Please refer to detours #1, #2 & #3

July 11 – July 13, 2017 Closure Will Include:

  • North bound I15
    • Closure of lanes #3 and #4 from 11 pm to 4 am.
    • Closure of north bound on-ramp at SR 79/Temecula Parkway from 11 pm to 4 am.
  • South bound I 15
    • Closure of lanes #3 and #4 from 11 pm to 4 am.
    • Closure of southbound  off-ramp at SR 79/Temecula Parkway from 9 pm to 5 am

Please refer to detours #2 & #3

Project updates for the week ending June 30, 2017 include:

  • Demolition, of the ARCO station is complete with removal of underground tanks and testing of soil samples.
  • Building of construction access road has begun.
  •        Short-term, single lane closures may be implemented on the northbound on- and off-ramps during non-peak hours.
  • Reminder– Park and Ride on Temecula Parkway and Front St will close after June 30, 2017. Please refer to http://www.ie511.org/rideshare/park-and-ridefor alternate park-and ride-sites.